MP2 conversion options - step 12 of 13
Select how to convert MP2 equipment criticalities into Infor EAM. In Infor EAM, the equipment criticality field is a field in which users must select from a valid criticality.
The grid displays the number of equipment criticalities that exist in Infor EAM. Once the equipment criticalities are displayed in the grid, the MP2 range of equipment criticalities can be set up in order to convert them into the proper Infor EAM equipment criticality.
MP2 equipment criticalities cannot overlap or users will receive an error. The system does allow gaps in numbering or a blank row in the grid. The equipment criticality field is not required in Infor EAM; therefore, MP2 equipment criticalities are not required to be mapped.
Here is an example of six equipment criticalities in Infor EAM:
Source Low Value | Source High Value | Destination Criticality | Description |
---|---|---|---|
1.00 | 1.99 | 1 | Emergency/Immediate |
2.00 | 2.99 | 2 | Urgent/Less than 24 hours |
3.00 | 3.99 | 3 | Required within 24-48 hours |
4.00 | 4.99 | 4 | Required within one week |
5.00 | 5.99 | 5 | Required within one month |
6.00 | 9999.99 | 6 | Required at first opportunity or shutdown |
If you follow this example, no equipment criticality in MP2 will be excluded in the conversion process. No MP2 equipment criticality can be less than 1.00, and by setting the source high value to 9999.99 on the last number, the conversion process will convert any equipment criticality greater than 6.00, and will fall into the 6 equipment criticality in Infor EAM.