Associating ERP resources to production requests
Associate ERP resources to selected production requests.
Note: The system will only associate ERP resources to
production requests with an Unfinished
Status.
A resource is a line of products, equipment, or materials used to complete a job.
To associate ERP resources to production requests:
- Select Work > Production Requests.
- Select the production request with which to associate ERP resources, and then click the Resources tab.
- Click Add Resource.
-
Specify this information:
- Resource
- Specify the resource to associate to the selected production request. The system automatically populates Accounting Entity and Name.
- Operation Sequence
- Specify the order in which this resource will be impacted when work is performed on the equipment.
- Cool-down Time (Hours)
- Specify the time it takes in hours for the resource line to cool down before performing production requests.
- Warm-up Time (Hours)
- Specify the time it takes in hours for the resource line to warm up before normal use.
- Downtime (Hours)
- Specify the expected downtime in hours for the selected production request.
- Offset
- Select to designate this resource line as offset, or that the resource impacted by down equipment will overlap with the previous resource.
- Offset Value
- Specify the amount of time in hours in which the resource impacted by down equipment, overlaps the previous resource.
-
Click
Submit.
Note: The system deletes a resource association only if the production request Status is Unfinished.
To associate resources to the production request not associated with the selected equipment, click All Resources. Select a resource, and then click Submit.
To refresh resources associated, select the resource record to refresh, and then click Refresh Resources.